Tesco Distribution Centre
Project Overview:
Location: Existing warehouse distribution centre
Total Space: 28,000 square metres
Office Space: 3,000 square metres
Completion Time: Tight time frame (exact duration unspecified)
Objective: To refurbish the warehouse for handover to the landlord
Scope of Work:
Internal Works:
Racking Removal: Complete removal of existing racking systems throughout the entire warehouse.
Fire Protection: Implementation of fire protection measures on the existing steel portal frame structure.
Floor Painting: Painting of the warehouse floor to improve durability and aesthetics.
M&E Services: Stripping back of mechanical and electrical services for refurbishment.
Office Refurbishment: Refurbishment of the office space, covering a total of 3,000 square metres.
External Works:
Concrete Repairs: Carrying out necessary repairs to the external concrete structures.
Fuel Bomb Tanks: Removal of existing fuel bomb tanks and restoration of the area.
Roof Repairs: Undertaking roof repairs using recoating systems to ensure longevity and leak prevention.
Cladding and Windows: Painting of existing cladding systems and windows to enhance appearance and protection.
Loading Docks: Servicing and remedial works on loading docks, including curtains and automatic roller shutters.